Kimpton Kawana Bay Construction Update

September 20th 2018

Kimpton Kawana Bay Construction Update

  • The superstructure of the Culebra building has been finished, and the building is nearing practical completion.
  • We are completing a second model room in the Culebra building based on an updated design (after receiving extensive feedback from Kimpton). This room will be a great way for visitors to the site to see what a finished room at the hotel will look like.



  • Following excavation, the foundations of the Juara building have been cast and construction has commenced on the concrete frame of the building.
  • In the next quarter, we anticipate completion of the construction drawings for Matura and for work on the foundation to start shortly thereafter. Once Matura is complete in late 2019, we will be ready to hand over both Phase 1 and Phase 2 of the project to Kimpton for them to open the hotel. The final Kiawah and Rekawa buildings will be completed a year later.

 

 

Pictured in the top center of the new rendering above is the Kiawah building – Phase 3 of Kimpton Kawana Bay. Following strong sales of the first two phases, Phase 3 sales have now been launched.

Categories: Kimpton Hotels